โ Back to Job Master (JOB-PAC843-2026)
๐ PAC 843 Complete Output Document Centre
Case Study Master Register ยท Vessel: PAC 843 ยท Client: PASUKAN POLIS MARIN ยท Ref: PO2600000000268877
Master Outputs
26
All 26 Registered
Generators Built
16 / 26
PCQ Bill (Row 10)
Authorized Ceiling
RM 34,921.64
PO2600000000268877
Contractor Claim
RM 40,606.26
Claimed Baseline
PCQ Deductions
-RM 458.66
Lampiran C & D
PCQ Approved
RM 40,147.60
Approved Settlement
Credit Variance
RM -5,225.96
NOT OFFICIAL CN
๐ Output Document Centre Policy:
All 26 operational, submission, payment, and completion documents evidenced by the PAC 843 case study are fully registered and visible below.
Incomplete generators are explicitly marked GENERATOR NOT YET IMPLEMENTED rather than hidden.
Official Credit Note is strictly marked EXTERNAL CONFIRMATION REQUIRED (Amount remains NULL until MOF/PDRM issuance).
A. SURVEY / PRE-REPAIR
Pre-docking inspection, technical condition assessment, scope specifications, and initial priced contractor bill.
#01 ยท PAC843_DOC_01_SURVEY_REPORT
Survey / Inspection Report
Laporan Pemeriksaan / Kerosakan Bot
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Authoritative technical survey and damage assessment prior to slipping and major refit.
| Primary Source: | PAC 843 Survey Report July 2026.xls |
| Source Sheet: | Sheet1 (2) |
| Output Format: | XLSX / PDF |
| Gap Classification: | Category I Fully implemented, tested, and verified |
#02 ยท PAC843_DOC_02_REPAIR_SCOPE
Repair Scope / Specification
Spesifikasi / Skop Kerja Pembaikan Asal
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Detailed work scope specifications and technical bill items for the Phase 1/2026 refit.
| Primary Source: | PAC 843 Blank.xlsx |
| Source Sheet: | PAC 843 Blank |
| Output Format: | XLSX / PDF |
| Gap Classification: | Category I Fully implemented, tested, and verified |
#03 ยท PAC843_DOC_03_PRICED_QUOTATION
Priced Quotation / Contractor Bill
Sebutharga / Senarai Kuantiti Berharga
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Contractor's original priced quotation schedule submitted to client totaling RM 37,859.04 prior to government LPO negotiation.
| Primary Source: | PAC 843 PPM KK AQ RM35,983.43.xlsx |
| Source Sheet: | PAC 843 RM35,983.43 |
| Output Format: | XLSX / PDF |
| Gap Classification: | Category I Fully implemented, tested, and verified |
B. APPROVAL / YARD
Government procurement sanction (LO/LPO), official vessel custody transfer to shipyard, and slipping notifications.
#04 ยท PAC843_DOC_04_GOVERNMENT_LO_LPO
Government LO / LPO Record
Pesanan Kerajaan (LO / LPO)
GENERATOR PENDING
GENERATOR NOT YET IMPLEMENTED
GENERATOR NOT YET IMPLEMENTED
Statutory government procurement authorization establishing legal repair ceiling of RM 34,921.64.
| Primary Source: | PAC 843 (ALUMINIUM) PPM KK Aqua Marine RM34,921.64.xlsx |
| Source Sheet: | Sheet1 |
| Output Format: | PDF / Government Form |
| Gap Classification: | Category B Data exists in database/pcq_engine; document template output not yet implemented |
Pending Information / Validation:
- Vote / Tender Ref (PDRM/PPMW4/PT(RS)/T1/05/2026)
- Date of Government Order
#05 ยท PAC843_DOC_05_VESSEL_HANDOVER_TO_YARD
Vessel Handing-Over to Yard
Borang Penyerahan Bot Kepada Limbungan
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Official protocol acknowledging delivery of PAC 843 into shipyard custody for docking operations.
| Primary Source: | PAC 843 HandingOver .docx |
| Source Sheet: | Document Body |
| Output Format: | DOCX / PDF |
| Gap Classification: | Category I Fully implemented, tested, and verified |
#06 ยท PAC843_DOC_06_UPSLIP_NOTIFICATION
Upslip / Slipping Notification
Surat / Sijil Menaikkan Landasan (Upslip)
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Formal notice and verification that PAC 843 was successfully hauled out of water onto slipway cradle.
| Primary Source: | PAC 843 Upslip.docx |
| Source Sheet: | Document Body |
| Output Format: | DOCX / PDF |
| Gap Classification: | Category I Fully implemented, tested, and verified |
C. REPAIR EXECUTION
Shipyard safety and coordination meetings (PSM), supplier materials procurement dossiers, and progress minutes.
#07 ยท PAC843_DOC_07_PSM_MINUTES
PSM Minutes (Project Safety Meeting)
Minit Mesyuarat Pra-Pelaksanaan / Keselamatan (PSM)
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Shipyard kick-off and project safety coordination minutes between Aqua Marine, Yard, and PDRM.
| Primary Source: | Minit PSM PAC 843.xlsx |
| Source Sheet: | Minit penyelarasan, MINIT PSM |
| Output Format: | XLSX / PDF |
| Gap Classification: | Category I Fully implemented, tested, and verified |
#08 ยท PAC843_DOC_08_MATERIALS_SUPPORTING_PACK
Materials / Supplier Supporting Pack
Dokumen Sokongan Pembekal & Bahan Gantian
GENERATOR PENDING
GENERATOR NOT YET IMPLEMENTED
GENERATOR NOT YET IMPLEMENTED
Dossier of supplier invoices, marine grade aluminium certificates, and outboard spares purchase evidence.
| Primary Source: | Pac 843 Supporting document.xlsx |
| Source Sheet: | General Supporting |
| Output Format: | PDF / XLSX |
| Gap Classification: | Category A Source exists in PAC 843 drive; system generator not yet implemented |
Pending Information / Validation:
- Sub-Tier Invoices and Delivery Orders
- Marine Grade 5083/5086 Aluminium Certification
- Antifouling & Primer Batch Numbers
#09 ยท PAC843_DOC_09_PROGRESS_MINUTES
Progress Meeting Minutes
Minit Mesyuarat Kemajuan Pembaikan
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Interim progress inspection minutes recording repair milestone completion percentages.
| Primary Source: | Minit Kemajuan PAC 843.xlsx |
| Source Sheet: | Cover Minit Kemajuan, MINIT KEM |
| Output Format: | XLSX / PDF |
| Gap Classification: | Category I Fully implemented, tested, and verified |
D. PCQ (PRICE EVALUATION COMMITTEE)
Detailed claim bill, PCQ minutes package, summary, technical justifications (Ulasan), signature pack, and Lampiran A-D statutory deduction schedules.
#10 ยท PAC843_DOC_10_PCQ_DETAILED_BILL
PCQ Detailed Bill / Claim Bill
Bil Terperinci Tuntutan PCQ (274 Baris)
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Authoritative submission claim bill detailing all 274 rows, formulas, LPO ceiling, contractor claim, and post-PCQ approved settlement.
| Primary Source: | PAC 843 PCQ bill.xlsx |
| Source Sheet: | PAC 843 RM35,983.43 |
| Output Format: | XLSX |
| Gap Classification: | Category I Fully implemented, tested, and verified |
#11 ยท PAC843_DOC_11_PCQ_MINUTES_PACKAGE
PCQ Minutes Package (Front Cover & Matters)
Muka Depan & Perkara-Perkara Minit PCQ
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Official government Price Evaluation Committee formal meeting proceedings and agenda.
| Primary Source: | MINIT PCQ - PAC 843.xlsx |
| Source Sheet: | MUKA DEPAN, PERKARA-PERKARA |
| Output Format: | XLSX / PDF |
| Gap Classification: | Category I Fully implemented, tested, and verified |
#12 ยท PAC843_DOC_12_PCQ_SUMMARY
PCQ Financial Summary Table
Jadual Ringkasan Kewangan PCQ
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Executive summary reconciling original quote, contractor claim, government deductions, and approved total.
| Primary Source: | MINIT PCQ - PAC 843.xlsx |
| Source Sheet: | Summary |
| Output Format: | XLSX |
| Gap Classification: | Category I Fully implemented, tested, and verified |
#13 ยท PAC843_DOC_13_PCQ_ULASAN
PCQ Technical Justification (Ulasan)
Ulasan Teknikal Jawatankuasa PCQ
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Technical findings and statutory justification rationale explaining reasons for price deductions.
| Primary Source: | MINIT PCQ - PAC 843.xlsx |
| Source Sheet: | ULASAN |
| Output Format: | XLSX / PDF |
| Gap Classification: | Category I Fully implemented, tested, and verified |
#14 ยท PAC843_DOC_14_PCQ_SIGN_KBK
PCQ Signatures & KBK Endorsement Pack
Pengesahan & Tandatangan Ahli PCQ / KBK
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Official endorsement sheet bearing signatures of Chief of Marine Engineering Division (KBK) and committee members.
| Primary Source: | MINIT PCQ - PAC 843.xlsx |
| Source Sheet: | SIGN KBK |
| Output Format: | XLSX / PDF |
| Gap Classification: | Category I Fully implemented, tested, and verified |
#15 ยท PAC843_DOC_15_LAMPIRAN_A
Lampiran A (Work/Material Not Performed)
Lampiran A: Kerja / Bekalan Tidak Dilaksanakan (RM 0.00)
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Statutory deduction schedule for approved scope items omitted entirely during docking.
| Primary Source: | MINIT PCQ - PAC 843.xlsx |
| Source Sheet: | Lampiran A |
| Output Format: | XLSX |
| Gap Classification: | Category I Fully implemented, tested, and verified |
#16 ยท PAC843_DOC_16_LAMPIRAN_B
Lampiran B (Unsatisfactory Work/Material)
Lampiran B: Kerja / Bekalan Tidak Mengikut Spesifikasi (RM 0.00)
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Statutory deduction schedule for substandard or defective works rejected by inspection.
| Primary Source: | MINIT PCQ - PAC 843.xlsx |
| Source Sheet: | Lampiran B |
| Output Format: | XLSX |
| Gap Classification: | Category I Fully implemented, tested, and verified |
#17 ยท PAC843_DOC_17_LAMPIRAN_C
Lampiran C (Scope Quantity Reductions)
Lampiran C: Pengurangan Kuantiti / Skop Kerja (RM 144.16)
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Statutory deduction schedule for reduced scope units: repainting boat number and draft marks reduced from 2 to 1 unit.
| Primary Source: | MINIT PCQ - PAC 843.xlsx |
| Source Sheet: | Lampiran C |
| Output Format: | XLSX |
| Gap Classification: | Category I Fully implemented, tested, and verified |
#18 ยท PAC843_DOC_18_LAMPIRAN_D
Lampiran D (Labour Hours Adjustments)
Lampiran D: Pengurangan Jam Bekerja / Kadar Buruh (RM 314.50)
GENERATOR BUILT
READY TO GENERATE
READY TO GENERATE
Statutory deduction schedule for labour hour reductions: 20 man-hours deducted across 8 scope items @ RM 18.50 x 0.85 = RM 314.50.
| Primary Source: | MINIT PCQ - PAC 843.xlsx |
| Source Sheet: | Lampiran D |
| Output Format: | XLSX |
| Gap Classification: | Category I Fully implemented, tested, and verified |
E. COMPLETION / HANDOVER
Undocking and sea trial requests, official work completion certification (SahKerja), final vessel handover, and warranty undertakings.
#19 ยท PAC843_DOC_19_DOWNSLIP_REQUEST
Downslip & Sea-Trial Request
Surat / Sijil Menurunkan Landasan & Ujian Laut
GENERATOR PENDING
GENERATOR NOT YET IMPLEMENTED
GENERATOR NOT YET IMPLEMENTED
Formal application to undock PAC 843 into water and conduct full engine and hull sea trials.
| Primary Source: | PAC 843 Downslip.docx |
| Source Sheet: | Document Body |
| Output Format: | DOCX / PDF |
| Gap Classification: | Category A Source exists in PAC 843 drive; system generator not yet implemented |
Pending Information / Validation:
- Vessel Name (PAC 843)
- Sea Trial Date
- Brilliant Marintime Shipyard
#20 ยท PAC843_DOC_20_SAHKERJA
Work Completion Certificate (SahKerja)
Sijil Pengesahan Kerja-Kerja Asal Dan Tambahan
GENERATOR PENDING
GENERATOR NOT YET IMPLEMENTED
GENERATOR NOT YET IMPLEMENTED
Authoritative certificate confirming 100% completion of approved original and additional scope items.
| Primary Source: | Pac 843 Supporting document.xlsx |
| Source Sheet: | SahKerja |
| Output Format: | XLSX / PDF |
| Gap Classification: | Category A Source exists in PAC 843 drive; system generator not yet implemented |
Pending Information / Validation:
- Vessel Name (BOT PAC 843 PPM KOTA KINABALU)
- PASUKAN POLIS MARIN
- GAN PING SIN (Pemilik, AQUA MARINE)
#21 ยท PAC843_DOC_21_SERAH_MENYERAH
Serah-Menyerah / Final Handover
Sijil Akuan Penerimaan Dan Penyerahan Bot/Kapal
GENERATOR PENDING
GENERATOR NOT YET IMPLEMENTED
GENERATOR NOT YET IMPLEMENTED
Statutory certificate of acceptance and redelivery of vessel back to PDRM Marine Police command.
| Primary Source: | Pac 843 Supporting document.xlsx |
| Source Sheet: | SerahMenyerah |
| Output Format: | XLSX / PDF |
| Gap Classification: | Category A Source exists in PAC 843 drive; system generator not yet implemented |
Pending Information / Validation:
- No. Botronda: PAC 843
- PASUKAN POLIS MARIN KOTA KINABALU
- GAN PING SIN (AQUA MARINE)
- Pegawai Penerima PDRM PPM
#22 ยท PAC843_DOC_22_WARRANTY_JAMINAN
Warranty / Surat Jaminan
Surat / Sijil Jaminan Mutu Kerja
GENERATOR PENDING
GENERATOR NOT YET IMPLEMENTED
GENERATOR NOT YET IMPLEMENTED
Contractor guarantee letter warranting workmanship and materials for the stipulated warranty term.
| Primary Source: | Pac 843 Supporting document.xlsx |
| Source Sheet: | Jamin |
| Output Format: | XLSX / PDF |
| Gap Classification: | Category A Source exists in PAC 843 drive; system generator not yet implemented |
Pending Information / Validation:
- Ketua Bahagian Kejuruteraan, PPM Wilayah 4 Sabah
- Workmanship & Spares Warranty Terms
- AQUA MARINE (GAN PING SIN)
F. BILLING / PAYMENT
Official contractor tax claim invoice, delivery note, and credit note adjustment (awaiting external confirmation).
#23 ยท PAC843_DOC_23_INVOICE
Invoice / Invois Rasmi
Invois Tuntutan Bayaran (RM 34,921.64)
GENERATOR PENDING
GENERATOR NOT YET IMPLEMENTED
GENERATOR NOT YET IMPLEMENTED
Official commercial invoice issued at the full LPO ceiling amount of RM 34,921.64 for government treasury billing.
| Primary Source: | Pac 843 Supporting document.xlsx |
| Source Sheet: | INV |
| Output Format: | XLSX / PDF |
| Gap Classification: | Category B Data exists in database/pcq_engine; document template output not yet implemented |
#24 ยท PAC843_DOC_24_DELIVERY_NOTE
Delivery Note / Nota Penghantaran
Nota Penghantaran (Delivery Note)
GENERATOR PENDING
GENERATOR NOT YET IMPLEMENTED
GENERATOR NOT YET IMPLEMENTED
Formal delivery acknowledgement for delivered works and replacement components accompanying the invoice.
| Primary Source: | Pac 843 Supporting document.xlsx |
| Source Sheet: | DN |
| Output Format: | XLSX / PDF |
| Gap Classification: | Category A Source exists in PAC 843 drive; system generator not yet implemented |
Pending Information / Validation:
- AQUA MARINE (R50817/2024)
- Delivery Note Serial Number
- PO2600000000268877
- Delivered Marine Repair Works & Spares List
#25 ยท PAC843_DOC_25_CREDIT_NOTE
Credit Note (Unconfirmed / Pending Evidence)
Nota Kredit (MENUNGGU PENGESAHAN LUAR)
GENERATOR PENDING
EXTERNAL CONFIRMATION REQUIRED
EXTERNAL CONFIRMATION REQUIRED
Official credit note adjusting invoice variance. Strictly unconfirmed in evidence; must not be fabricated.
| Primary Source: | Pac 843 Supporting document.xlsx |
| Source Sheet: | CN (shows RM 0.00 / blank unit price) |
| Output Format: | XLSX / PDF |
| Gap Classification: | Category G External confirmation required (e.g. MOF/PDRM credit note issuance) |
Pending Information / Validation:
- Official Credit Note instruction from Ministry of Finance / PDRM
- Confirmed Credit Note Serial Number & Issuance Date
G. SUPPORTING EVIDENCE
Comprehensive supporting evidence dossier and supplier verification pack.
#26 ยท PAC843_DOC_26_EVIDENCE_PACK
Supporting Evidence Pack
Pakej Bukti Sokongan & Resit Pembelian
GENERATOR PENDING
GENERATOR NOT YET IMPLEMENTED
GENERATOR NOT YET IMPLEMENTED
Consolidated evidence file including photo records of repairs, technician timesheets, and delivery dockets.
| Primary Source: | Pac 843 Supporting document.xlsx |
| Source Sheet: | Multiple Sheets |
| Output Format: | PDF / XLSX / PPTX |
| Gap Classification: | Category A Source exists in PAC 843 drive; system generator not yet implemented |
Pending Information / Validation:
- Photographic and Delivery Receipts
- Work Verification Cross-References
๐ Aqua Marine Case-Study Gap Classification Reference
Category A: Source exists in PAC 843 drive; system generator not yet implemented
Category B: Data exists in database/pcq_engine; document template output not yet implemented
Category C: Data model or schema extension required
Category D: Document record not yet registered in database
Category E: Source evidence missing from project archive
Category F: Source data conflicting across documents
Category G: External confirmation required (e.g. MOF/PDRM credit note issuance)
Category H: System / Owner architectural decision required
Category I: Fully implemented, tested, and verified